Category: Expansion

Campbell Clinic Wolf River Grand Opening

https://www.campbellclinic.com/campbell-clinic-wolf-river-grand-opening/

On Thursday, December 5, 2019, we hosted the grand opening of our new $40 million, 120,000 square-foot facility – equipped with state-of-the-art amenities and our Accel Performance and Wellness Center named in honor the S. Terry Canale Family. 


Weekly Construction Update: October 28, 2019

https://www.campbellclinic.com/weekly-construction-update-october-28-2019/

WORK PERFORMED THIS WEEK: Continued electrical rough-in on the first and fourth floors.  Continued installing overhead lights and trim-out on first and fourth floors. Continued wiring transformers in electrical rooms.  Continued working on underground site electrical.  Installed light poles. Continued installing plumbing overhead on fourth floor.  Continued installing plumbing fixtures throughout building.  Continued installation of […]


Weekly Construction Update: October 21, 2019

https://www.campbellclinic.com/construction-update-october-21-2019/

WORK PERFORMED THIS WEEK: Continued electrical rough-in on the first and fourth floors.  Continued installing overhead lights and trim-out on the first and fourth floors.  Continued wiring transformers in electrical rooms.  Continued working on underground site electrical. Continued installing overhead plumbing on the fourth floor. Continued installing plumbing fixtures throughout building.  Continued installation of med-gas […]


Weekly Construction Update: October 14, 2019

https://www.campbellclinic.com/construction-update-october-14-2019/

Work Performed This Week: Continued electrical rough-in on the first and fourth floors.  Continued installing overhead lights and trim-out on first and fourth floors. Continued wiring transformers in electrical rooms.  Continued working on underground site electrical. Continued installing plumbing overhead on fourth floor.  Continued installing plumbing fixtures throughout building.  Continued installation of med-gas booms in […]


Weekly Construction Update: October 7, 2019

https://www.campbellclinic.com/construction-update-october-7-2019/

WORK PERFORMED THIS WEEK: Continued electrical rough-in on the first and fourth floors.  Installed overhead lights and trim on first, third and fourth floors.  Continued wiring transformers in electrical rooms.  Continued working on underground site electrical. Continued installing overhead plumbing on the fourth floor.  Installed plumbing fixtures throughout building.  Continued installation of med-gas booms in […]


Weekly Construction Update: September 30, 2019

https://www.campbellclinic.com/construction-update-september-30-2019/

WORK PERFORMED THIS WEEK: Continued electrical rough-in on the first and fourth floors.  Continued installing overhead lights and trim on first and third floors.  Finished installing conduit for pool.  Continued wiring transformers in electrical rooms.  Continued working on underground site electrical. Continued plumbing installation overhead on first and fourth floors.  Continued installing plumbing fixtures. Continued […]


Weekly Construction Update: September 23, 2019

https://www.campbellclinic.com/construction-update-september-23-2019/

WORK PREFORMED THIS WEEK Continued electrical rough-in on the first and fourth floors.  Continued installing overhead lights and trim out on first and third floors. Continued installing conduit for pool.  Continued wiring VAV boxes.  Continued wiring transformers in electrical rooms.  Continued working on underground site electrical. Continued installing plumbing overhead on first and fourth floors.  […]


Weekly Construction Update: September 3, 2019

https://www.campbellclinic.com/weekly-construction-update/

Work Performed this Week: Installed electrical overhead and in-wall rough-in on the first and fourth floors. Continued installing overhead lights on first and third floors.  Continued installing conduit for pool.  Wired VAV Boxes.  Continued wiring transformers in electrical rooms.  Continued working on underground site electrical. Continued plumbing installation of overhead on first, third and fourth […]


Construction Update: August 26, 2019

https://www.campbellclinic.com/construction-update-august-26-2019/

WORK PERFORMED THIS WEEK: Continued installing electrical overhead and in-wall rough-in on the first and fourth floors. Installing overhead lights on first floor.  Installed conduit for pool.  Installed third floor lights.  Wired VAV Boxes.  Continued wiring transformers in electrical rooms.  Continued working on underground site electrical. Continued plumbing install overhead on first, third and fourth […]


Construction Update: August 19, 2019

https://www.campbellclinic.com/construction-update-august-19-2019/

WORK PERFORMED THIS WEEK Installed electrical overhead and in-wall rough-in on the first and fourth floors. Installed overhead lights on first floor.  Installed conduit for pool. Installed third floor lights and tied them off.   Wired VAV Boxes. Placed permanent power.  Mounted transformers in electrical rooms. Continued installing overhead and in-wall on first, third and fourth […]


For appointments call
901-759-3111