Category: Expansion

Construction Update: May 13, 2019

https://www.campbellclinic.com/construction-update-may-13-2019/

WORK PERFORMED THIS WEEK: Detailed stair no. 2. Shipped, staged and installed screen wall steel. Continued electrical overhead and in-wall rough-in on the first and third floors. Continued underground feed for the generator power. Installed wall and overhead rough-in on the first, second and third floors. Worked on rain leaders and wet columns. Continued layout […]


Construction Update: May 6, 2019

https://www.campbellclinic.com/construction-update-may-6-2019/

WORK PERFORMED THIS WEEK: Continued detailing stair no. 2. Continued shipping, staging and installing screen wall steel. Continued installing electrical overhead and in wall rough-in on the first and third floors. Continued installing wiring up the VAV boxes. Continue underground feed for the generator power. Plumbers installed in wall and overhead rough-in on the first, […]


Construction Update: April 29, 2019

https://www.campbellclinic.com/construction-update-april-29-2019/

WORK PERFORMED THIS WEEK: Detailed stair no. 2. Installed HVAC curbs on the roof. Installed decking on the east half roof. Tied in-roof drains on the second floor. Shipped/staged/installed screen wall steel. Continued installing electrical overhead and in wall rough-in on the first and third floors. Continued installing wiring up the VAV boxes on the […]


Construction Update: April 22, 2019

https://www.campbellclinic.com/construction-update-april-22-2019/

WORK PERFORMED THIS WEEK:   Began detailing on stair no. 2. Installed HVAC curbs on the roof. Shipped, staged and installed curtain wall steel, and installed decking on the east half roof. Prepped and poured the second and third floor canopies. Continued electrical overhead and in wall rough-in on the first and third floors. Wired […]


Construction Update: April 15, 2019

https://www.campbellclinic.com/construction-update-april-15-2019/

WORK PERFORMED THIS WEEK: Continued erection of east half steel canopies. Installed stair no. 2 and continued shipping and staging steel. Installed decking on the east half roof. Decked south side canopies. Prepped and poured the electrical/mechanical pads. Extended electrical overhead and in wall rough-in on the first and third floors. Continued underground electrical work […]


Construction Update: April 8, 2019

https://www.campbellclinic.com/construction-update-april-8-2019/

WORK PERFORMED THIS WEEK: Continued erecting east half steel. Installed stair no. 2, and continued shipping and staging steel. Installed decking on the east half fourth floor and roof. Decked south side canopies. Prepped and poured the fourth floor east half slab. Installed electrical overhead and in wall rough-in on the first and third floors. […]


Construction Update: April 1, 2019

https://www.campbellclinic.com/construction-update-april-1-2019/

WORK PERFORMED THIS WEEK: Continued erecting, shipping and staging east half steel. Installed decking on the east half fourth floor and roof. Prepped and poured stair no. 1. Prepped and poured cáfe area. Installed electrical overhead and in wall rough-in on the first and third floors. Laid out sleeves on the east half fourth floor […]


Construction Update: March 25, 2019

https://www.campbellclinic.com/construction-update-march-25-2019/

WORK PERFORMED THIS WEEK: Continued erection of east half steel. Continued shipping and staging steel. Installed decking on the east half fourth floor and roof. Prepped and poured the east half second and third floor decks. Detailed stair no. 1 to be poured. Laid electrical overhead rough-in on the third floor. Laid out sleeves on […]


Construction Update: March 18, 2019

https://www.campbellclinic.com/construction-update-march-18-2019/

WORK PERFORMED THIS WEEK: Continued erection of east half steel. Continued shipping and staging steel. Continued decking the east half second and third floor decks. Poured stair no. 3. Began electrical overhead rough-in on third floor. Laid out sleeves on the east half second and third floor deck. Installed plumbing hangers and pipe on second […]


Construction Update: March 11, 2019

https://www.campbellclinic.com/construction-update-march-11-2019/

WORK PERFORMED THIS WEEK: Continued erection of east half steel. Continued shipping and staging steel. Continued decking the east half second and third floor decks. Erected and detailed stair no. 3. Roughed in electrical overhead on third floor and laid out sleeves on the east half third floor deck. Installed plumbing hangers and pipe on […]


For appointments call
901-759-3111