WORK PERFORMED THIS WEEK: Continued erection of east half steel. Continued shipping and staging steel. Finished decking the west half roof. Began decking the east half second and third floor decks. Poured the fourth floor deck. Set and poured stair no. three. Laid out electrical wiring for lights on the first floor. Finished installing plumbing […]
WORK PERFORMED THIS WEEK: Continued erection of east half steel. Finished decking the west half fourth floor. Began decking the west half roof. Poured the second floor deck. Prepped and poured the fourth floor deck. Finished installing electrical sleeves on the fourth floor deck. Continued installing plumbing sleeves on the fourth floor deck. Continued shipping […]
WORK PERFORMED THIS WEEK: Began erection of east half steel. Finished west half steel erection. Began decking the west half fourth floor. Poured the third floor deck. Prepped and poured the second floor deck. Finished installing electrical sleeves on the second floor deck. Finished installing plumbing sleeves on the second floor deck. Continued shipping and […]
WORK PERFORMED THIS WEEK: Installed deck on the second floor of the west half steel. Continued installing electrical sleeves on the second and third floor deck. Continued installing plumbing sleeves on the second and third floor deck. Continued shipping and staging steel. Continued west half steel erection. Continued pouring anchor bolt diamond blockouts. Prepped and […]
WORK PERFORMED THIS WEEK: Continued underground electrical in the parking lots. Began plumbing work on the first floor restrooms. Continued shipping and staging steel. Continued west half steel erection. Installed stair tower on southwest corner of the building. Began installing sleeves on elevated decks of the west half steel. Poured electrical room blockout. Began pouring […]
WORK PERFORMED THIS WEEK: Continued underground electrical. Continued shipping and staging steel. Continued west half steel erection. Brought electrical room block-out up to subgrade and prepped to pour. Continued installing the deck on the third floor of the west half steel. Continued work on west side private drive entrance. Continued work on the underground storm […]
WORK PERFORMED THIS WEEK: Continued underground electrical. Continued shipping and staging steel. Continued west half steel erection. Set west half stairs. Began installing the deck on floors two and three of the west half steel. Began excavation and installation of canopy foundations. Poured canopy foundations. Continued work on west side private drive entrance. Continued underground […]
WORK PERFORMED THIS WEEK: Continued underground electrical & plumbing. Continued shipping and staging steel. Continued west half steel erection. Prepped east half of the building pad for slab pour. Placed underslab aggregate on east side. Poured the east half slab. Continued work on west side private drive entrance. Continued underground storm drainage inlet & manhole […]
WORK PERFORMED THIS WEEK: Continued underground plumbing and electrical. Continued shipping and staging steel. Continued west half steel erection. Prepped east half of the building pad for slab pour. Placed underslab aggregate on east side. Continued work on west side private drive entrance. Continued underground storm drainage inlet and manhole lid placement. STATISTICS: The crane […]
WORK PERFORMED THIS WEEK: Continued underground plumbing and electrical. Continued shipping and staging steel. Continued west half steel erection. Prepped east half of the building pad for slab pour. Placing underslab aggregate on east side. STATISTICS: The crane that will be used to hang all the structural steel arrived on site this week. It arrived […]
For appointments call
901-759-3111