Continued erection of east half steel canopies. Installed stair no. 2 and continued shipping and staging steel.
Installed decking on the east half roof. Decked south side canopies.
Prepped and poured the electrical/mechanical pads.
Extended electrical overhead and in wall rough-in on the first and third floors.
Continued underground electrical work for the generator power, rough-in exterior lights and card readers on the southeast corner of the building.
Installed in wall rough-in and overhead water main on the third floor. Installed roof drains on the second floor canopy. Began core drilling on exterior wall.
Continued layout and installation of VAV duct/boxes on the first and third floors. Worked on mechanical chases. Delivered RTUs.
Continued interior wall layout, including erection of studs and installation of door frames on the first and third floors. Continued layout of the fourth floor.
Began spray foam insulation on exterior wall.
Continued fireproofing the east and west half steel.
Finished hanging north side precast, and continued shipping and staging precast. Moved crane to the west side.
Continued caulking between the precast.
Continued installation of window frames.
STATISTICS:
The concrete and brick façade currently being installed is composed of 373 individual panels. These are cast at a plant in Ashland City, Tennessee and delivered via trucks to the site.
The panels are hoisted using cranes and welded back to the concrete and steel structure, fitting together like a large and heavy jigsaw puzzle. The largest panel weighs approximately 25,000 pounds.