Installed HVAC curbs on the roof. Shipped, staged and installed curtain wall steel, and installed decking on the east half roof.
Prepped and poured the second and third floor canopies.
Continued electrical overhead and in wall rough-in on the first and third floors. Wired up the VAV boxes on the first floor.
Continued underground feed for the generator power.
Tied in-roof drains on the second floor.
Continued layout and installation of VAV duct/boxes on the third floor. Worked on mechanical chases and RTUs.
Continued interior wall layout, erection of studs and installation of door frames on the first and third floors. Continued layout of the fourth floor.
Continued spray foam insulation on exterior wall.
Continued fireproofing the west and east half steel.
Continued hanging west side precast. Shipped and staged precast.
Delivered new crane.
Continued caulking between the precast.
Continued installation of window frames.
STATISTICS:
The concrete and brick façade currently being installed is composed of 373 individual panels. These are cast at a plant in Ashland City, Tennessee and delivered via trucks to the site.
The panels are hoisted using cranes and welded back to the concrete and steel structure, fitting together like a large and heavy jigsaw puzzle. The largest panel weighs approximately 25,000 pounds.