Construction Update: December 28, 2018

December 28, 2018

WORK PERFORMED THIS WEEK:

  • Continued underground plumbing and electrical.
  • Continued shipping and staging steel.
  • Continued west half steel erection.
  • Prepped east half of the building pad for slab pour.
  • Placing underslab aggregate on east side.

STATISTICS:

  • The crane that will be used to hang all the structural steel arrived on site this week. It arrived in several pieces and was assembled on site over two days.
  • After being assembled the crane was then moved into position on the southwest side of the building pad where the erection process will begin.


For appointments call
901-759-3111