Construction Update: February 18, 2019
February 18, 2019
WORK PERFORMED THIS WEEK:
- Began erection of east half steel.
- Finished west half steel erection.
- Began decking the west half fourth floor.
- Poured the third floor deck.
- Prepped and poured the second floor deck.
- Finished installing electrical sleeves on the second floor deck.
- Finished installing plumbing sleeves on the second floor deck.
- Continued shipping and staging steel.
- Began interior wall layout.
- Continued underground storm drainage inlet construction, manhole lid placement and backfill.