Construction Update: February 25, 2019

February 25, 2019

WORK PERFORMED THIS WEEK:

  • Continued erection of east half steel.
  • Finished decking the west half fourth floor.
  • Began decking the west half roof.
  • Poured the second floor deck.
  • Prepped and poured the fourth floor deck.
  • Finished installing electrical sleeves on the fourth floor deck.
  • Continued installing plumbing sleeves on the fourth floor deck.
  • Continued shipping and staging steel.
  • Began interior wall layout.
  • Began fireproofing the west half steel.
  • Continued underground storm drainage inlet construction, manhole lid placement and backfill.

STATISTICS

The precast erection process will begin within the next week on the southwest corner of the building. A crane will be brought in to pick up the panels and set them in place. The panels that are being set are the finished exterior of the building.