Construction Update: June 24, 2019

June 24, 2019

WORK PERFORMED THIS WEEK:
  • Continued installation of overhead and in-wall rough-ins on the first to the fourth floors.
  • Installed electrical feeders from the first to the fourth floors.
  • Continued installation of permanent power.
  • Wired and installed VAV boxes.
  • Insulated and fire caulked pipes.
  • Installed plumbing in-wall & overhead rough-in on the first through fourth floors.
  • Installed ducts on the fourth floor and tied in the chases.
  • Installed the HVAC units on the roof.
  • Continued interior wall layout, erection of studs and installation of door frames on first through fourth floors.
  • Continued topping out on the third floor.
  • Continued installation of drywall insulation on the first and third floors.
  • Installed termination bar and termination bar backing while working on the sidewall.
  • Continued installation of sprinkler pipe on the first floor.
  • Tested sprinkler pipe on the third floor.
  • Continued spray foam insulation on the exterior wall.
  • Continued caulking between the precast and exterior window frames.
  • Continued setting exterior windows and frames.
  • Continued working on retaining wall on the Campbell Clinic Drive.

STATISTICS:

  • By the end of the job, there will have been approximately 420,000 square feet of drywall installed throughout the building. This is enough square footage of drywall to cover up the Memphis Redbirds jumbotron almost 117 times.
  • Once the job is complete the framing contractor (Ranger Construction) will have installed approximately 240,000 linear feet of metal framing studs. This is enough to cover just over 45 miles, which will make it around the Shelby Farms Greenline trail about 4.5 times.
  • Roughly 8,000 square feet of glass will be used for the north elevation of this building. This is enough material to cover the basketball court of the Memphis Grizzlies.