Weekly Construction Update: September 23, 2019

September 23, 2019

WORK PREFORMED THIS WEEK

  • Continued electrical rough-in on the first and fourth floors. 
  • Continued installing overhead lights and trim out on first and third floors.
  • Continued installing conduit for pool. 
  • Continued wiring VAV boxes. 
  • Continued wiring transformers in electrical rooms. 
  • Continued working on underground site electrical.
  • Continued installing plumbing overhead on first and fourth floors. 
  • Finished up med gas lines on the fourth floor. 
  • Continued installing plumbing fixtures.
  • Continued installation of suite arrays. 
  • Continued installing grilles on first and third floors.
  • Continued installation of framing and drywall on the first and fourth floors.
  • Finished installing hard ceilings on the first floor. 
  • Framed the north canopy. 
  • Continued finishing the operation room ceilings. 
  • Framed the slam ceilings.
  • Continued hanging ACM panels on the north elevation and begin hanging ACM on the south canopy.
  • Continued installing branch lines on the second floor for the sprinkler system.
  • Installed structural supports for the nana wall systems.
  • Installed sub-base for the exterior turf field. 
  • Formed and poured curb and gutter around the building. 
  • Continued bringing the site to grade. 
  • Began cementing the soil.
  • Continued installing flooring on the first, third, and fourth floors. 
  • Installed wall protection on all floors.
  • Continued north elevator installation. 
  • Inspected elevator 1 and is operable. 
  • Began installation of south elevators. 
  • Continued installing elevator door frames.
  • Continued installing wire for the security camera and control systems on the third floor.
  • Began installation of wiring for the exterior doors and interior card readers on first and third floor.
  • Continued painting on first and fourth floors.
  • Began installation of toilet partitions.
  • Continued installation of rubber flooring system on the first floor.
  • Continued installation of interior doors and glass. 
  • Installed storefront in the HydroWorx® area.
  • Continued installing millwork on the first, third and fourth floors.
  • Began installing Mid-South imaging in the RAD rooms.
  • Began installing Steris in the operation rooms.
  • Installed site irrigation.

STATISTICS

  • With the elevation of the roof sitting just over 60’ from ground level, one could see about 9 miles when on the roof.
  • The new Campbell Clinic building will not only have patients from all over the world, it will also be full of products from all over the world. For example, the tiling that will be at the front entrance on